copyProgress at the new Wiseburn campus at 201 N. Douglas St. marches on in 2016 as demolition has wrapped up its final stages. Today, the crew poured 100 yards of concrete in preparation for strengthening the foundation of the building.

Next week, the crew will begin installing concrete caissons and making steel structural upgrades inside the building.

In April, electricians and plumbers will advance inside the building, while framers seal up the exterior of the building.

The project is moving forward on schedule. The new campus, the future home of Da Vinci Communications, Da Vinci Design, Da Vinci Science, and the Wiseburn and Da Vinci administrative offices, is slated to open in the fall of 2017 for the 2017-18 school year.